Update to roadworks around Wychbold.
From the newsletter bulletin #7 issued by Public Liaison Officers: Andy Lee and Neil Hallam on 13th March.
This letter is to update you about the closure of M5 Junction 5, and how it will affect the residents of Wychbold.
Essential maintenance work on the A38/M5 J5 roundabout was conducted between 12th February to March 8th which was earlier than predicted and on time.
This work has now been completed and all restrictions have been lifted.
Heidelberg Materials and National Highways would like to thank the residents of Whychbold for their patience and understanding whilst this essential work was completed and to those that were able to attend the drop-in session held at McDonalds on 6th March.
Feedback is always important, and we do act on any information and suggestions made.
As a result of this project Heidelberg Materials will be completing ‘Social Value’ to put something back into the community.
As a result, we will be resurfacing the road to the Parish Hall and completing school visits providing education/ career packages.